Beaumont Square | Development Progress

Here you will find the latest progress reports and images for the construction of Beaumont Square in Plymouth, UK. Following the £266 Million regeneration project announced in 2003, Plymouth began to attract successful business, education facilities, living spaces, and recreation opportunities for citizens, investors, and visitors.

This attraction is evident in the Beaumont Square project, which will provide a total of 39 student studio apartments over 2 apartment blocks (Block A = 22 studios | Block B = 17 studios). The location is also ideal, less than 1 mile from Plymouth University, the popular harbour district, and the city centre.

Furthermore, tenants in Beaumont Square will be able to enjoy their fully self-contained studio in safety with a manned reception area and the security of 24 hour CCTV, giving both the students and parent’s full piece of mind.

This is a great opportunity to tap into Plymouth’s lucrative student market. These hassle-free, fully managed apartments provide investors with an assured 3 year NET rental of 8%.

Beaumont Square | Development Progress 05/06/2018

This update about the development progress of Beaumont Square in Plymouth is dated from 05/06/2018. Additional images and key points from the Beaumont Square site can be found below.

Main Points:

  • Works at the development recommenced in May 2018 and are now fully underway
  • In order to complete the development, new funding had to be obtained

Beaumont Square | Development Progress 20/11/2017

This update about the development progress of Beaumont Square in Plymouth is dated from 20/11/2017. Additional images and key points from the Beaumont Square site can be found below.

Main Points:

  • Block B is complete, with the final snagging works taking place currently.
  • Block A will be completed for Christmas with the first fixes.
  • Plastering complete with a little more decorating and snagging to undertake and then final fix of the studios will take place.

Beaumont Square | Development Progress 27/09/2017

This update about the development progress of Beaumont Square in Plymouth is dated from 27/09/2017. A few additional images from the Beaumont Square site can be found below.

Beaumont Square | Development Progress 24/07/2017

This update about the development progress of Beaumont Square in Plymouth is dated from 24/07/2017. The vinyl flooring is now being laid down according to plan and is coming along nicely. This is just a quick visual update from last week, with a couple images below showing the floor quality and style. We’re really loving the colour!

Beaumont Square | Development Progress 15/07/2017

This update about the development progress of Beaumont Square in Plymouth is dated from 15/07/2017. There are now over 40 workers working on the site every day, plus overtime to make sure this project is brought in on time for September completion.

Important points are below.

Main Points:

  • Vinyl flooring is already on site with fitter booked for Monday Start.
  • Kitchens will also be fitted from Monday.
  • All the indoor decorating is being finalised.

Beaumont Square | Development Progress 29/06/2017

This update about the development progress of Beaumont Square in Plymouth is dated from 29/06/2017. We are pleased to bring you a further construction update for the Beaumont Square project as the timber frame of the second floor is now complete.

Important points are below.

Main Points:

  • Block work is complete up to the 1st Floor in Block A and timber Frame is up to the 2nd Floor.
  • Pipework in to Ground Floor to feed up to the rest of the Block and up into the boiler room in Block B as well as roof Trusses complete.
  • 60% of Firewall built from Top Floor Ceiling to Underside of Roof in Block B and insulation done to all ceilings.

Beaumont Square | Development Progress 20/06/2017

This quick update about the development progress of Beaumont Square in Plymouth is dated from 20/06/2017. We are pleased to bring you a few further images on the progress of Beaumont Square, fresh from the construction site in Plymouth!

Beaumont Square | Development Progress 12/05/2017

This update about the development progress of Beaumont Square in Plymouth is dated from 12/05/2017. We are pleased to bring you a further construction update for the Beaumont Square project.

Important points are below.

Main Points:

  • We are now up to roof on block B.
  • Block A ground floor is completed and are well under way with the next floors.
  • Electrics and plumbing will be starting next week.

Beaumont Square | Development Progress 25/04/2017

This update about the development progress of Beaumont Square in Plymouth is dated from 25/04/2017. We are pleased to provide a construction update from the developer of the Beaumont Square project with several aspects of construction now completed.

Important points are below.

Main Points:

  • We have begun work on the internal walls of block B which we are hoping to complete by the end of next week.
  • Block A has started going up and we are looking at around 6-8 weeks to have this up to wall plate.
  • We are still on track for Q3 completion.

Beaumont Square | Plymouth

To invest in Beaumont Square or learn more about the development, please click the link below.

Investment Overview: Beaumont Square | Plymouth

Development Enquiry Form