James Street | Development Progress

Here you will find the latest progress reports and images for the construction of the James Street in Bradford, UK.

James Street Apartments is a refurbishment of a stunning grade II listed building in the very centre of the city of Bradford.

Located a short walk from the £260m Broadway Shopping and Leisure complex and with a whole host of bars and restaurants, James Street Apartments is the perfect residential hotspot for those looking to embrace a more urban lifestyle. The Bradford Interchange, that is being tipped for a high speed rail linking Manchester and Leeds is also minutes away.

This stunning residential building will offer a mix of 31 studios apartments, spread over 4 floors. Aside from it’s unique features and historic nature, owners can benefit from a fully hands-off management program by the award winning Priestley Lettings, generating NET yields in excess of 8.5% per annum.

James Street | Development Progress 17/04/2019

This update about the development progress of James Street in Bradford is dated from 17/04/2019.

Please see the photos from James Street construction in the gallery below.

James Street is still on schedule for practical completion 06/05/2019.

James Street | Development Progress 28/02/2019

This update about the development progress of James Street in Bradford and is dated from 28/02/2019.

James Street is well on schedule for practical completion 06/05/2019.

Current works:

  • Paint work is in progress
  • Flooring is complete on the top 2 floors
  • Plumbing/electric works almost complete
  • Joinery work is in progress
  • Kitchens are currently being installed

James Street | Development Progress 18/12/2018

This update about the development progress of James Street in Bradford and is dated from 18/12/2018.

We are 8 week into our construction programme here. Full demolition and strip out is complete. All floors have been levelled with new acoustic floating floor laid to each level. Our partition walling is 50% complete with boarding going up and first fix electrics and plumbing well underway. We are on course for our predicted Q2 completion here. 31 flats and 3 ground floor retail units!