One Islington Plaza | Development Progress

Here you will find the latest progress reports and images for the construction of One Islington Plaza in Liverpool, UK. One Islington Plaza will offer 317 studio and en-suite clusters, ideal for both undergraduate and mature students, in Liverpool’s academic hub – The Knowledge Quater.

The en-suite units will have a power shower, study desk, double bed, flat-screen TV and high-speed broadband. A lot of research and thought has been placed into every aspect of the development, ensuring residents get the best offering available in the city.

Residents living in en-suite units will enjoy fully fitted communal kitchens. The studio apartments will have the same facilities as the en-suites along with a private kitchen. There will be flat-screen TVs throughout the communal areas, as well as a cinema room and a games room with pool tables, foosball, ping pong and game stations.

With an assured yield of 8% for the first 3 years, these apartments represent an excellent investment opportunity which we anticipate will sell fast.

One Islington Plaza | Development Progress 14/11/19

This update about the development progress of One Islington Plaza in Liverpool is dated from 14/11/19. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing.

Download Update

One Islington Plaza | Development Progress 20/07/19

This update about the development progress of One Islington Plaza in Liverpool is dated from 20/07/19. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below:

External Works

  • CP board 100% installed
  • Insulation is complete
  • 99% windows installed
  • Pictura cladding installed 99%
  • Aluminium cladding has progressed 99%
  • Roof installed 100%
  • Envelope works are all but complete with final low-level cladding, parapet and window works being completed via scissor lifts

Internal Works

  • Beam and block floor completed
  • Ground floor walls completed
  • Lift installed 99%
  • Ceilings completed
  • Internal doors complete
  • Mechanical, electrical and plumbing works 98% progressed
  • Furniture, fixtures and equipment 70% installed

Download Update

One Islington Plaza | Development Progress 26/03/19

This update about the development progress of One Islington Plaza in Liverpool is dated from 26/03/19. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below:

External Works

  • CP board 100% installed
  • Insulation is complete
  • 98% windows installed
  • Pictura cladding installed 99%
  • Aluminium cladding has progressed 99%
  • Roof installed 98%
  • Envelope works are all but complete with final low-level cladding, parapet and window works being completed via scissor lifts

Internal Works

  • Beam and block floor completed
  • Ground floor walls 95% installed
  • Lift installed 99%
  • 99% progression of internal partitions
  • Ceilings 98% installed
  • Internal doors 95% complete
  • Mechanical, electrical and plumbing works 95% progressed
  • Furniture, fixtures and equipment 45% installed
  • Floors 9 down to 3 are being final fixed decorated with upper floors all but complete

Download Update

One Islington Plaza | Development Progress 18/02/19

This update about the development progress of One Islington Plaza in Liverpool is dated from 18/02/19. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below

External Works

  • CP board installed 100%.
  • Insulation 100% installed.
  • Windows installed to 90% with 7% materials on site.
  • Pictura cladding installed 97% and remaining materials on site.
  • Aluminium cladding 97% installed, 3% on site.
  • Roof installed to 98% with remaining materials on site.
  • Internal Works

    • Beam and block floors complete.
    • 94% ground floor walls installed with 6% materials on site.
    • Lift installed to 99%.
    • Internal partitions installed to 97% with 3% materials on site.
    • Ceilings installed 87% with 13% materials on site.
    • Internal doors are 90% complete, 10% materials on site.
    • Mechanical, electrical and plumbing works 90% installed with 10% materials ready on site.
    • Furniture, fixtures and equipment 40% installed with 30% materials now on site.
    • Floors 9 down to 3 are being final fixed and decorated, with upper floors nearing completion

    Download Update

One Islington Plaza | Development Progress 29/01/2019

This update about the development progress of One Islington Plaza in Liverpool is dated from 29/01/2019. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below

External Works

  • CP board installed 100%
  • Insulation is 100% installed
  • Glazing is completed to 89% with 5% materials ready and on site
  • Pictura cladding installed to 97% completion
  • Aluminium cladding 95% complete with 5% remaining materials on site
  • Roof installed to 98%

Internal Works

  • Beam and block floor installed 100%
  • Ground floor walls are 90% complete
  • The lift is 99% installed
  • Internal partitions are 95% complete
  • Ceilings are 90% installed
  • Internal doors are 80% complete
  • Mechanical, electrical and plumbing first fix works are 98% complete with 2% materials on site
  • Mechanical, electrical and plumbing second fix works are installed to 70% with 20% materials on site
  • Decorations are 80% complete
  • FF&E 45% complete

Download Update

One Islington Plaza | Development Progress 20/12/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 20/12/2018. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below

External Works

    External Works

  • CP Board installed 100%.
  • Insulation installed 100%.
  • Windows are installed to 90%.
  • Pictura cladding installed 96%.
  • Aluminium cladding installed 90%.
  • Roof is 98% complete.

    Internal Works

  • Beam and block floor installed 100%.
  • Ground floor walls installed 85%.
  • The lift is 99% complete.
  • Internal partitions are 95% installed.
  • Ceilings 87% installed.
  • Internal doors 80% installed.
  • Mechanical, electrical plumbing (MEP) first fix works 95% installed.
  • Other 5% of materials are now onsite.
  • MEP second fix works 70% installed.

Download Update

One Islington Plaza | Development Progress 28/11/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 28/11/2018. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below

External Works

  • CP board is installed to 98%.
  • Insulation is 95% installed.
  • The windows are 55% installed.
  • Pictura cladding is 95% installed.
  • Aluminium cladding has been started and is 30% complete.
  • The roof is now 98% complete.

Internal Works

  • Beam and block floors are 100% complete.
  • Ground floor walls are 80% installed.
  • The lift is installed to 80%.
  • Internal partitions are 85% in place.
  • Ceilings have been installed to 40%.
  • Internal doors have been progressed to 40%.
  • Mechanical, electrical and plumbing 1st fix works are 95% complete.
  • Mechanical, electrical and plumbing 2nd fix works are 35% installed.

Download Update

One Islington Plaza | Development Progress 15/11/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 15/11/2018. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below

Internal Works

  • Beam and block floor completed.
  • Ground floor block walls 95% installed.
  • Blockwork to lift shaft 100% complete.
  • Internal partitions 75% installed.
  • 35% of ceilings installed.
  • Internal door installation 20% complete.
  • MEP 1st fix works 90% materials on site.
  • MEP 2nd fix works 30% materials on site.

Download Update

One Islington Plaza | Development Progress 19/09/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 19/09/2018. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below

External Works

  • CP Board 50% included.
  • Insulation 75% installed.
  • Windows are 30% complete.
  • Pictura cladding is 70% complete.
  • Aluminum cladding materials are on site.
  • Roof installation nearly complete at 98%.

Internal Works

  • Beam and block flooring is 100% complete.
  • Ground floor block walls are installed to 90%.
  • Blockworks lift shaft is complete.
  • Internal partitions installed at 68%.
  • Ceilings installed are 30% complete.
  • Internal doors are 15% complete.
  • MEP 1st fix 80% installed.
  • MEP 2nd fix works have begun and are 20% underway.

Download Update

One Islington Plaza | Development Progress 24/08/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 24/08/2018. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

  • Works Progressed
  • CP board and membranes 100% installed.
  • Cladding is approximately 40% installed.
  • Roof is 95% complete.
  • Lift shaft is complete.
  • Curtain wall framing is approximately 20% complete.
  • Beam & block floor installation is complete.
  • Ground floor block walls 70% installed.
  • Mechanical & electrical second fix has commenced on floors 8-10.
  • Mechanical & electrical first fix is nearing completion on floors 4-7.
  • Plasterboard partitions installed on floors 6-10.

Download Update

One Islington Plaza | Development Progress 31/07/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 31/07/2018. The latest One Islington Plaza Construction Update shows substantial progress at the site with the main points detailed below.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

  • board and insulation is 90% installed
  • Cladding and window installation has commenced
  • The roof is 95% complete
  • The lift shaft is complete
  • Beam and block floor installation is complete
  • Ground floor block walls are 30% installed
  • Mechanical and electrical first fix works are complete on floors 6-10
  • Plasterboard partitions have been installed on floors 6-10

One Islington Plaza | Development Progress 29/06/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 29/06/2018. The latest One Islington Plaza Construction Update shows substantial progress at the site with installation of beam and block floors at 90%.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

  • Floors 6 to 10 – 80% of internal plasterboard installed
  • Floors 2 to 5 – 75% of steel partitioning installed
  • Installation of SFS board 100%

One Islington Plaza | Development Progress 25/05/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 25/05/2018. The latest One Islington Plaza Construction Update shows substantial progress at the site with underfloor drainage now 100% complete.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

  • Underfloor drainage is now 100% complete
  • 70% of internal plasterboard is installed on floors 6 to 10
  • SFS board installation is now almost complete at 75%

One Islington Plaza | Development Progress 17/04/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 17/04/2018. Construction is progressing well at One Islington Plaza on Devon Street with no adversities according to the latest construction update by the developer.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

  • The internal partitions have been set up ready for installation on floors 4 to 10.
  • Mast hoists are now 100% completely installed.
  • All the internal insulation is on site.

One Islington Plaza | Development Progress 26/02/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 26/02/2018. Building Consents visited site on 7th February 2018 to carry out a routine inspection, particularly in relation to the floor and rebar installation. No adverse comments were raised.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

  • Steel frame works are now 100% complete
  • Concreting to all floors is 75% complete
  • Mast hoists are 50% installed

One Islington Plaza | Development Progress 31/01/2018

This update about the development progress of One Islington Plaza in Liverpool is dated from 31/01/2018. Entering February, works on-site are progressing well. Steelwork erection commenced on 25th October 2017 and EPCL can now confirm that all precast concrete stairs have been installed and metal decking on levels 1-5 has commenced.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

  • Concrete floors are due to commence within the next period and the steel frame will be completed imminently.
  • Over the next period, EPCL are to liaise with the Main Contractor Urban Student Life (USL) regarding audio visual installation requirements at the ground floor as well as study cluster cubicle power requirements within the amenity space.
  • Building Consents continue to carry out regular inspections. No adverse comments have been raised.

One Islington Plaza | Development Progress 20/12/2017

This update about the development progress of One Islington Plaza in Liverpool is dated from 20/12/2017. Works are progressing well on site this month. Following the site meeting on Tuesday 19th December, the programme was discussed between all parties.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

  • Concurrent works and an extra gang are necessary for the steelwork installation programme.
  • EPCL have been advised that two steel erection gangs are on site.
  • As it stands, Building Consents continue to carry out regular inspections. No adverse comments have been raised.

One Islington Plaza | Development Progress 21/11/2017

This update about the development progress of One Islington Plaza in Liverpool is dated from 21/11/2017. The show flat is now complete, which you can see in the below images along with images from the construction site. Please view the walk through video below.

If you would like to make an appointment to come view the recently completed show flat, please don’t hesitate to get in touch with one of our consultants today.

One Islington Plaza | Development Progress 30/09/2017

This update about the development progress of One Islington Plaza in Liverpool is dated from 30/09/2017. Images from the Islington Plaza construction site can be seen below.

One Islington Plaza | Development Progress 31/08/2017

This update about the development progress of One Islington Plaza in Liverpool is dated from 31/08/2017. Images from the Islington Plaza construction site can be seen below.

One Islington Plaza | Development Progress 31/07/2017

This update about the development progress of One Islington Plaza in Liverpool is dated from 31/07/2017. Images from the Islington Plaza construction site can be seen below.

One Islington Plaza | Development Progress 21/03/2017

This update about the development progress of One Islington Plaza in Liverpool is dated from 21/03/2017. Images from the Islington Plaza construction site can be seen below, with workmen now onsite.

One Islington Plaza | Liverpool