One Wolstenholme Square | Development Progress

Here you will find the latest progress reports and images for the construction of One Wolstenholme Square in Liverpool, UK. These modern self-contained studio apartments are located in a very desirable city centre location near the World Heritage waterfront of Liverpool.

All studios will be finished to a modern high standard with walnut finish flooring throughout, walnut laminate doors with brushed steel hardware, dulux trade matt paint to walls, dulux trade satinwood to woodwork, TV aerial, SKY TV points, and low voltage LED lighting.

Kitchens will have contemporary high gloss white units with push to open doors & soft-close mechanisms. Contrasting grey work top, stylish stainless steel oven, hob, sink and taps and an integrated fridge/freezer

These apartments are 17% below market value with a return on investment from 86% over 5 years and 8% NET yield assured for 3 years. Free high-spec furniture packs are available for Aspen Woolf investors. All apartments are fully managed armchair investments.

One Wolstenholme Square | Development Progress 12/12/2018

This update about the development progress of One Wolstenholme Square in Liverpool is dated from 02/10/2018.

The appended photographs taken week commencing 17 September 2018 show the following progress on site:

Block A (73 units)

  • Completion December 2017
  • Block B (149 units)

  • Completion April 2018
  • Block C (96 units)

  • Completion achieved 7 September 2018
  • Block D (114 Units)

  • Substructures completed
  • Steel frame, upper floors and stairs complete
  • Windows 95% complete
  • Brickwork complete
  • Metal stud partitioning complete
  • Plastering complete
  • Kitchens, tiling and floor finishes complete
  • Furniture complete
  • Snagging at Level 6
  • Power on achieved 12 December 2018 and meters due w/c 17 December 2018
  • Block E (38 units)

  • Substructures complete
  • Frame complete
  • Metal decking complete
  • Partitioning commenced on level 3
  • M&E first fix commenced
  • Download Update

    One Wolstenholme Square | Development Progress 02/10/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 02/10/2018.

    The appended photographs taken week commencing 17 September 2018 show the following progress on site:

    Block A (73 units)

    • Completion December 2017

    Block B (149 units)

    • Completion April 2018

    Block C (96 units)

    • Completion achieved 7 September 2018

    Block D (114 Units)

    • Substructures completed
    • Steel frame, upper floors and stairs complete
    • Windows 95% complete
    • Brickwork 95% complete
    • Metal stud partitioning commenced on all levels
    • Plastering commenced on Level 7
    • First fix M&E complete
    • Kitchens, tiling and floor finishes at Level 6
    • Furniture complete on Level 3
    • Snagging at Level 3

    Block E (38 units)

    • Substructures complete
    • Frame 99% complete
    • Metal decking to Level 5

    Download Update

    One Wolstenholme Square | Development Progress 10/09/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 10/09/2018.

    The appended photographs taken week commencing 3 September 2018 show the following progress on site:

    • Block A (73 units)
      – Completion December 2017
    • Block B (149 units)
      – Completion April 2018
    • Block C (96 units)
      – Completion achieved 7 September 2018
    • Block D (114 Units)
      – Substructures completed
      – Steel frame, upper floors and stairs complete
      – Windows 95% complete
      – Brickwork 95% complete
      – Metal stud partitioning commenced on all levels
      – Plastering commenced on Level 6
      – First fix M&E complete  Kitchens, tiling and floor finishes at Level 5
      – Furniture complete on Level 3
      – Snagging at Level 3
    • Block E (38 units)
      – Substructures complete
      – Frame commenced

    Download Update

    One Wolstenholme Square | Development Progress 03/08/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 03/08/2018.

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Expected Completion:

    • Block C – WYG apartment inspections and back checking complete. “Power on” achieved Friday 29 June 2018, apartment meters installed, communal meter due 3 August 2018 and completion 17 August 2018.
    • Block D – Windows 95% complete
      – Brickwork 90% complete
      – Plastering commenced on Level 5
      – First fix M&E at Level 6
      – Kitchens, tiling and floor finishes at Level 4
      – Furniture complete on Level 1
      – Snagging inspection for Level 1 scheduled for 8 August 2018
    • Block E – Substructures complete
      – Frame due w/c 13 August 2018

    One Wolstenholme Square | Development Progress 15/06/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 15/06/2018.

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Expected Completion:

    • Block C – CWYG apartment inspections complete with back-checking and communal areas
      outstanding.
    • Block D – Substructures completed
      – Steel frame, upper floors and stairs complete
      – Windows 75% complete
      – Brickwork 50% complete
      – Metal stud partitioning commenced on all levels
      – Plastering commenced on Level 2
      – First fix M&E at Level 3
      – Kitchens, tiling and floor finishes at Level 1
    • Block E – Site clearance commenced,Substructures start June 2018

    One Wolstenholme Square | Development Progress 04/05/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 04/05/2018.

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Expected Completion:

    • Block B – Completion April 2018
    • Block C – Contractor snagging and cleaning to Level 4
    • Block D – Weatherboarding to elevations and windows commenced to Levels 1-6
    • Block E – Substructures start June 2018

    One Wolstenholme Square | Development Progress 06/04/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 06/04/2018. Mechanical and electrical works – tested and commissioned

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Expected Completion:

    • Block B – w/c 16 April 2018
    • Block C – June 2018
    • Block D – August 2018
    • Block E – February 2019

    One Wolstenholme Square | Development Progress 13/03/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 13/03/2018. mechanical and electrical works – tested and commissioned

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Snagging commenced to levels 5 in Block B
    • M&E second fix commenced on Level 1-5 in Block C
    • Ground floor slab reinforcement 50% complete in Block D

    One Wolstenholme Square | Development Progress 09/02/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 09/02/2018. mechanical and electrical works – testing and commissioning has commenced to levels 1 & 2

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Snagging commenced to levels 2 & 3
    • M&E second fix commenced on Level 1-3
    • Steel frame approximately 95% complete – due for completion 26 January 2018

    One Wolstenholme Square | Development Progress 10/01/2018

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 10/01/2018.

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Final testing and commissioning complete and awaiting certification/Building Control sign-off on Block A.
    • Mechanical and electrical works – testing and commissioning outstanding on  Block B.
    • Brickwork approximately 95% complete on Block C

    One Wolstenholme Square | Development Progress 04/12/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 04/12/2017.

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Snagging and inspections ongoing in Block A.
    • Finishing trades progressing with tiling, kitchens and plank flooring at approximately 90% complete in Block B.
    • Brickwork approximately 75% complete in Block C

    One Wolstenholme Square | Development Progress 10/11/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 10/11/2017.

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Snagging and inspections ongoing in Block A.
    • Finishing trades progressing with tiling, kitchens and plank flooring at approximately 85% complete in Block B.
    • M&E first fix now approximately 90% complete in Block C and Block D has commenced with substructures.

    One Wolstenholme Square | Development Progress 11/10/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 11/10/2017. Block A’s testing of electrical installation is pending connection with the substation. The delay is due to the electric substation, thus completion is due in October 2017

    The report attached goes into more detail about what works have been completed and how things are progressing in the 4 different Blocks. Important points are below.

    Main Points:

    • Furniture installations complete on first and second floors of Block B.
    • Internal partitioning commenced to first and second floors of Block C.
    • Substructures due to commence 23 October 2017 for Block D.

    One Wolstenholme Square | Development Progress 05/09/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 05/09/2017. Testing of electrical installation is currently pending whilst connection with substation is established.

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Snagging and inspections ongoing in Block A.
    • Finishing trades progressing with tiling, kitchens and plank flooring at approximately 20% complete.
    • Upper floor decking complete in Block C.

    One Wolstenholme Square | Development Progress 31/07/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 31/07/2017. We are happy to bring you another update to the One Wolstenholme Square project. Please also find new images from the build site below.

    The report attached goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Tiling and sanitaryware 100% complete in Block A.
    • Insitu concrete upper floors 100% complete in Block B.
    • Substructures completed and steelwork frame commenced on site in Block C.

    One Wolstenholme Square | Development Progress 03/07/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 03/07/2017. The Employer appointed Mees Demolition to carry out the demolition of the existing buildings on the site, which is now complete.

    The report also goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Floor finishes to apartments approximately 100% and window installation approximately 99% complete in Block A.
    • Facing brickwork 15% complete and concrete foundation bases 100% complete in Block B.
    • Substructures completed and steelwork frame commenced on site in Block C.

    One Wolstenholme Square | Development Progress 30/05/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 30/05/2017. The One Wolstenholme Square construction continues to progress well.

    The report also goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • 2nd sample studios on first floor complete with proposed furniture in Block A
    • First fix electrical commenced in Block B.
    • First delivery of structural steelwork due w/c 12 June 2017 in Block C

    One Wolstenholme Square | Development Progress 10/05/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 10/05/2017. A review of site logistics for access to each block for construction in conjunction with the interface with the adjacent hotel project has been carried out with the Contractor and anticipated completion dates can be found in the below report

    The report also goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Substructures complete in Block A.
    • Concrete foundation bases 100% complete in Block B.
    • Block C substructures start week commencing 8 May 2017.

    One Wolstenholme Square | Development Progress 13/03/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 13/03/2017. Site access and logistics have unfortunately caused slight delays to the construction process, so Block C foundations can’t begin until the frame for Block B is complete due of the delivery and distribution of larger materials. Similarly, construction of Blocks D and E are further complicated by access for the hotel at the rear of the site.

    The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Windows installation approximately 50% complete in Block A.
    • Single ply membrane roof complete in Block A.
    • Pre-cast concrete stairs installation commenced and installed in Block B.

    One Wolstenholme Square | Development Progress 08/02/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 08/02/2017. In Block A the brickwork facing is in progress and the sample studios on the first floor are being fitted with kitchens, tiling is in progress and the floor finishes are all taking place. Block B is also progressing well; steel frames are in production and expected on site week commencing 6 February 2017.

    The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • Pre-cast concrete stairs installed in Block A.
    • External wall lining at Levels 1 to 9 in Block A.
    • Concrete foundation bases 100% complete in Block B.

    One Wolstenholme Square | Development Progress 17/01/2017

    This update about the development progress of One Wolstenholme Square in Liverpool is dated from 17/01/2017. We’re pleased to announce the substructures and steel frame is complete in Block A. The steel frame for Block B will be on site by the end of January 2017.

    The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points: 

    • Steel frame complete in Block A.
    • Upper floors complete in Block A.
    • Concrete foundation bases 95% complete in Block B.

    One Wolstenholme Square | Liverpool

    To invest in One Wolstenholme or learn more about the development, please click the link below.