When you invests in RopeWalks you gain an assured income of 8% NET for 3 years, and are sure to benefit from attractive capital growth and constant demand due to the unbeatable central location. RopeWalks offers a fantastic opportunity to enter Liverpool’s lucrative buy-to-let property market with a fully hands off investment managed and let by an established managing company on your behalf.

RopeWalks | Development Progress 19/06/2019

This update about the development progress of RopeWalks in Liverpool is dated from 19/06/2019. The latest images from the RopeWalks site can be found in this update.

  • The building works are carrying on and final pieces of internal works are being completed.
  • The stairs and corridor to the Duke Street entrance has now been completed. All the corridor ends have now been tied in and plastered.
  • The lift is now fully installed and will be commissioned in the next two weeks. There are some small infills being completed on the door edges.
  • The rooms are 95% completed on the ground floor. First, second and third floors are complete with just snagging and small areas remaining.
  • Fourth fifth and sixth-floor rooms are 90% complete
  • All footpaths have been reinstated and the fire alarm has been installed.
  • One unit is still in process of completing with elevation with final pieces of cladding needed to be fitted. Following that te scaffolding can come down in the courtyard.
  • Completion is on track for August 2019.
  • RopeWalks | Development Progress 10/04/2019

    This update about the development progress of RopeWalks in Liverpool is dated from 10/04/2019.

    The latest images from the RopeWalks site can be found by following the link below:

    See the images

    RopeWalks | Development Progress 15/01/2019

    This update about the development progress of RopeWalks in Liverpool is dated from 15/01/2019. The latest images from the RopeWalks site can be found in this update.

      Interior of the building 80% Complete

    • We are now in the final stages of closing off the building with the first 4 floors now having there second coat of paint and Glossing of the Skirting Boards and window cills
    • All the bath rooms have now been installed up to the 4th Floor and work has started on the final two floors which leaves just 15 rooms to complete with Bathrooms and Kitchens
    • Iron Mongery has been fitted to all front doors and internal doors.on the first 4 floors
    • The corridor lights and first coat painting has been completed up till the 4th Floor
    • The lift is onsite and due to be installed this month
      External building 85% Complete

    • There are small elements of cladding which is currently being completed
    • All 4 pods are now built and 70% cladder
    • All the infills have been done where scaffolding has penetrated the building.
    • Electrical services have started to be commissioned and signed off
    • There is a small amount of scaffolding on the 4th Floor terrace which is due to be removed this week
    • The footpath has now been reinstated
    • We are expecting completion of the building and sign off early Q2 2019

    RopeWalks | Development Progress 27/11/2018

    This update about the development progress of RopeWalks in Liverpool is dated from 27/11/2018. The latest images from the RopeWalks site can be found in this update.

    This summary covers work completed up until 22nd November 2018 .

    • 49 Kitchens have been fitted and bathroom corridor lights are going to be completed by Tuesday next week.
    • All corridors are now plastered and the entrance hall is boarded.
    • The windows are getting plated and capped and will be completed by Tuesday at the front of the building and the back section will be completed by the end of next week. The cladding on the front of the building will be completed by Tuesday.
    • The elevation is currently being installed in the back and as soon as complete the first three floors are expected to be snagged and signed off by end of next week.
    • Scaffolding is down and the building is taking shape and is looking fantastic.
    • Completion target has been amended to end of January.

    Download Update

    RopeWalks | Development Progress 13/09/2018

    This update about the development progress of RopeWalks in Liverpool is dated from 19/07/2018. The latest images from the RopeWalks site can be found in this update.

    This summary cover work completed up till the end of August 2018

    • 90% of all external windows have been fitted and the Culrtain walling and windows are 50% complete
    • The Kitchens have now started to be fitted with over 20 rooms complete, along with the skirting boards and doors have started to be fitted.
    • The mechanical contractors have now powered up the building with all the mains installed lighting and switches are currently being installed in to all rooms.CCTV has been installed and working.
    • The internal walls are all currently being plastered and the painter is working through the rooms on first and second coat the corridors have started to be closed off ready for plastering.
    • The front facade has now been refurbished and the scaffolding is due to be dismantled.
    • Drainage is fully installed and the building has been fully pressure text all has been signed
    • The building is starting to be closed down with ground to 4 th floor nearly complete.
    • The external brick work is 90% complete with the final bricks getting laid . The cladding has is now on site and is currently being installed this will be completed in the next 3 weeks.
    • Shower units and sanitary ware has started to be installed
    • Council Building control have been regularly on site and been happy with the quality of the workmanship and all fire protections have been adhered to every individual apartment is being checked and signed off.

    Download Update

    RopeWalks | Development Progress 19/07/2018

    This update about the development progress of RopeWalks in Liverpool is dated from 19/07/2018. The latest images from the RopeWalks site can be found in this update.

    RopeWalks | Development Progress 19/06/2018

    This update about the development progress of RopeWalks in Liverpool is dated from 19/06/2018. The latest images from the RopeWalks site can be found in this update.

    • The curtain walling is now going in along with the cladding all windows have been fitted.
    • Apartments are starting to get skimmed ready for the skirting and doors to be fitted.
    • Balconies have been installed.
    • Main electrics have been brought into the building with distribution boards all completed.
    • The pluming has been completed on levels 0-5 and the boilers have started to be installed the first 30 boilers have been installed.
    • The painter is due to start painting all rooms and corridors W/C 25th June.
    • The Cladding is starting this Monday.
    • Estimated completion; End of August

    RopeWalks | Development Progress 27/03/2018

    Set for completion end of June.

    • 85% of windows now fully installed. Completion of installation week 1 April.
    • Brick facia 70% complete. Completion week 2 April.
    • Cladding and Curtain walling due to be installed in the week 3 April.
    • Plastering, skirting, doors commencing week 2 April.
    • Kitchen & bathroom installations begin week 4 April.

    Eldonian Brookhaven currently working with the following companies to let the properties out prior to official completion:

    http://mtdresidentiallettings.co.uk

    https://www.redwingliving.co.uk

    We are pleased to say that interest has been impressive with a waiting list already in place.

    RopeWalks | Development Progress 11/01/2018

    This update about the development progress of RopeWalks in Liverpool is dated from 11/01/2018. The latest images from the RopeWalks site can be found below. The attached report goes into more detail about the work completed this month.

    RopeWalks | Development Progress 23/10/2017

    This update about the development progress of RopeWalks in Liverpool is dated from 23/10/2017. The latest images from the RopeWalks site can be found below. The build is coming along very nicely.

    RopeWalks | Development Progress 21/09/2017

    This update about the development progress of RopeWalks in Liverpool is dated from 21/09/2017. The building is really coming together and we’re excited to bring you another update for the RopeWalks project, which covers work carried out up until the end of August.

    The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below along with a few further images.

    Main Points:

    • The final two floors on the block are now under construction.
    • The internal walls have been set out and are under construction.
    • The steel has now been fire treated.

    RopeWalks | Development Progress 31/07/2017

    This update about the development progress of RopeWalks in Liverpool is dated from 31/07/2017. We’re very excited to say that the first 3 stories of the steel frame have been erected! It’s starting to slowly look like a building instead of just a dig site with foundations in place. The metal decking has been installed on the ground floor, first and second floor. The decking has now been stud welded and the concrete is being poured the first week in August. Now we’ll really start to see the building take shape as the foundations are in place.

    The developer is currently on target to meet the end of December projected completion date and they have brought in some more contractors to fit in with this time frame. Great news!

    The attached report goes into more detail about what works have been completed and how things are progressing. Important points are below.

    Main Points:

    • The drainage and ground slab is now underway and is expected to be completed in the next three weeks.
    • The dryliners and M&E teams will be appointed the first week in August, and are due to start August 14th.
    • The final 3 floors are due to be erected. The roofing contractor can then install the roof along with the relevant solar panels, which will make the building more energy efficient and environmentally friendly.

    RopeWalks | Development Progress 22/06/2017

    This update about the development progress of RopeWalks in Liverpool is dated from 22/06/2017. From the below video, you will see that the foundations are in and the steel frame has now been fitted and poured with further work being complete on them. The first phase will be completed at the end of this month.

    The developer is currently on target to meet the end of December projected completion date and they have brought in some more contractors to fit in with this time frame.

    Please find our main points from the latest update below along with a quick video update on the construction phase of RopeWalks.

    Main Points:

    • Stairs to be installed 28th-29th June.
    • Scaffolding and Floors will be delivered and installed 3rd July.
    • Tanking and Drainage will begin 3rd-4th July.

    RopeWalks | Development Progress 08/05/2017

    This update about the development progress of RopeWalks in Liverpool is dated from 08/05/2017. From the below images, you will see that the foundations are in and the pads for the steel frame have now been fitted and poured

    Please find out main points from the report below.

    Main Points:

    • The Steel frame is due to be erected on the 15th May and pre-cast stairs will begin to be put in at the end of May.
    • The metal decking and floors are due to be fitted at the beginning of June.
    • Bricks have been ordered and the external envelope is due to commence on the 5th June.

    RopeWalks | Development Progress 20/03/2017

    This update about the development progress of RopeWalks in Liverpool is dated from 20/03/2017. From this report you will see that the ground works and laying of the foundations are coming along nicely.

    Please find out main points from the report below.

    Main Points:

    • Ground works and laying of foundations has begun at RopeWalks.

    RopeWalks | Development Progress 17/02/2017

    This update about the development progress of RopeWalks in Liverpool is dated from 17/02/2017. We’re happy to announce that scaffolding is now in place and workmen are on site. We hope to bring you news on ground works and laying of the foundations in the coming weeks.

    Please find out main points from the report below.

    Main Points:

    • Scaffolding is in place and workmen are on site.