Stone Cross House | Development Progress

Here you will find the latest progress reports and images for the construction of the Stone Cross House in Bolton, UK.
Located right in the heart of Bolton, within the Church Wharf regeneration area, Stone Cross House will be Bolton’s first high specification, “City Living” style development, and will include much sought after Smart home technology.

Stone Cross House | Development Progress 18/03/20

This update about the development progress of Stone Cross House in Bolton is dated from 18/03/20.

The internal areas of the show apartments have been completed and decorated with interior design finished. We are currently finishing the balcony areas. We anticipate these will be ready for prospective tenants and investors to view in May 2020.

Stone Cross House | Development Progress 23/01/20

This update about the development progress of Stone Cross House in Bolton is dated from 23/01/20.

Kitchens are fitted (minus appliances) on all floors apart from the ground floor and bathrooms are all fitted down to the second floor. On the top floor, the painting, plumbing and electrics are complete in all of the apartments. They’re also carpeted, apart from in the show apartment. The smoke vents are being fitted throughout the building.

Work is beginning on the landscaping to the rear, with the space being cleared ready for tarmacking and fresh lines being painted on the car park. Planting beds will be dug out ready for planting at a later stage.

Stone Cross House | Development Progress 16/12/19

This update about the development progress of Stone Cross House in Bolton is dated from 16/12/19.

The ultra modern high end kitchen has now begun to be installed in the show apartment on the top floor. Once complete this will give interested parties the ability to view the fantastic quality and finish of the fitted kitchens in each apartment as well as other luxury features and finishes.

Stone Cross House | Development Progress 20/11/19

This update about the development progress of Stone Cross House in Bolton is dated from 20/11/19.

Corridors now beginning to take shape. Show apartment is now ready for the Bi Folding patio doors. Roof ventilation now installed servicing all 61 Apartments.

Stone Cross House | Development Progress 06/09/19

This update about the development progress of Stone Cross House in Bolton is dated from 06/09/19.

First Fix Plumbing and Electrics.

First Fix is now well underway on Stonecross House, as the top two floors really begin to take shape. Mains boards have been installed and first fix plumbing for the Kitchens and Bathrooms is complete on these floors. Work is also progressing well in the installation of the mechanical ventilation that will run throughout the development. Please feel free to watch the recent drone video taken of the site to give a real feel for Stonecross House and its surroundings:

Watch Video

Stone Cross House | Development Progress 10/08/19

This update about the development progress of Stone Cross House in Bolton is dated from 10/08/19.

First Fix Upper Floors & Drone Video.

Recent good weather and the installation of the construction lift at the rear of the project have enabled the build to really begin to move now with the top two floors fully partitioned and first fix plumbing and electrics underway. Heaton Group have taken advantage of the recent fine weather and produced a Drone video of the site and local area to give interested parties a real feel of how Stone Cross House is going to become part of the Church Wharf regeneration scheme transforming this fantastic town.

Stone Cross House | Development Progress 17/07/19

This update about the development progress of Stone Cross House in Bolton is dated from 17/07/19.

Partition Construction Underway. New Floors Complete.

New drainage system and floors are now installed across all 5 floors. The partition team have now begun the construction of each unit on the top floor in readiness for first fix electrics and plumbing.

Stone Cross House | Development Progress 08/07/19

This update about the development progress of Stone Cross House in Bolton is dated from 08/07/19.

Rip out complete. New drains and floor screeding underway.

The internal demolition is now complete with all new door openings formed. Work is well underway installing the new drainage system and insulated floors. The lift has also now been erected at the rear of the site ready for the delivery of the partition walls that will soon be installed.

Stone Cross House | Development Progress 01/06/19

This update about the development progress of Stone Cross House in Bolton is dated from 01/06/19.