Asquith House | Development Progress

Here you will find the latest progress reports and images for the construction of Asquith House in Leeds, UK. Asquith House is a purpose built off plan student development comprising of a total of 298 en-suite bedrooms and studios across two separate buildings.

All student bedrooms are arranged in apartments of 4 and 6 bedrooms, each sharing a communal area complete with kitchen, dining area and lounge. Studio rooms are more private and contain their own kitchenette. Situated on Servia Road, the site is a convenient 5 minute walk to The University of Leeds and Leeds Metropolitan University campuses and just a 10 minute walk into the city centre.

Students will benefit from living and studying within a thriving student hub with an abundant of cafes, bars, restaurants and shops. This development is excellently placed to meet this huge demand- this investment opportunity is certainly not to be missed!

Asquith House | Development Progress 30/06/2017

This update about the development progress of Asquith House in Leeds is our second update dated from 30/06/2017. Construction works are beginning to edge ever closer to completion, which is expected from next month in July.

The attached report has images and goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • All boarding works and plastering to the internal walls are now complete on all floors.
  • All fire stopping procedures are now complete on all floors.
  • Snagging works are now underway, which is undertaken by the construction company to rectify any minor faults before the final handover.

Asquith House | Development Progress 25/05/2017

This update about the development progress of Asquith House in Leeds is our very first update dated from 25/05/2017. Interior work at Asquith House is progressing well. Practical completion date is June 2017.

The attached report has images and goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • Boarding works to the internal walls have now started on the 6th floor and will start on the 5th next week.
  • Floor protectors have been laid out on all floors from the 6th floor to the 2nd, ahead of the commencement of fire stopping work. The fire stopping is due for completion by the middle of next week.
  • The retaining wall to the grounds is now complete.

Development Enquiry Form