Bridgewater Wharf | Development Progress
Standing up to eight storeys high and spread out over five distinctive blocks, Bridgewater Wharf Manchester is an iconic addition to the skyline. When on-site amenities are taken into account – such as secure cycle storage, a communal residents lounge, a private gymnasium and parking on selected units including electric charging points – it is clear that Bridgewater Wharf is an outstanding opportunity for investors.
Each apartment will be completed with contemporary fixtures and fittings which will raise the bar when it comes to modern living in this busy city. In addition, many apartments include spacious balconies which overlook Salford and Manchester, providing the sort of views which are in high demand. Bridgewater Wharf is the perfect home for people looking to live close to both Manchester city centre and the picturesque Salford Quays waterfront, which includes MediaCityUK. Both are only a short distance from the development, as are all of the restaurants, shops, bars and public transport options that anyone could ask for. When on-site amenities are taken into account – such as secure cycle storage, a communal residents lounge, a private gymnasium and parking on selected units including electric charging points – it is clear that Bridgewater Wharf is an outstanding opportunity for investors.
Bridgewater Wharf, Manchester | December 2022 Construction Update
Dear Investors,
There has been some fantastic progress on site over the course of the past two months with the main focus being on Block’s B,C & D. Dry liners have had the largest presence on site over the course of November and December concentrating on boarding out the remaining apartments and communal areas in Blocks B,C & D. We have also had flooring contractors present on site during this period screeding the floors in the apartments ready for internal fit out. Further details broken up by block below-
Block B
Dry liners have been present in Block B completing the internal board out on levels 1&2 ready for the Electrical contractors to begin 1st fix electrics in the new year.
Block C
• Tilers have been on site throughout December and have completed the tiling on levels 1&2 with level 3 scheduled to begin in early January.
• Plumbers have been working in conjunction with the tilers installing the baths on levels 1,2&3 ready for the tiling work to commence, this will continue with works to levels 4&5 in early January
• Joiners and kitchen installers have been present on Block C throughout December installing kitchens to levels 1&2, this will also continue through to next year with works to levels 3&4 starting in early January
• Dry liners have now finished boarding out Block C and just await a spell of improved weather to enable final skim on the top level’s
Block D
• Dry liners have made great progress on Block D with internals on levels 3&4 now complete and works on level’s 5&6 to start in the new year
• Electrical and plumbing contractors have also made great progress in Block D working in collaboration with the dry liners and working their way up through the level’s
Upcoming Works
Block’s B,C & D-
Works to Blocks B,C & D will continue in line with the above update with the various contractors working their way up the levels in each block to close out each individual works package.
Block’s A & E-
Works to Blocks A&E are set to be ramped up in the new year with the site taking delivery of a large order of Glasroc board earlier this month. This is in preparation for works to commence on making both blocks weather tight and ready for internal works to begin.