Austin Hall | Development Progress
Here you will find the latest progress reports and images for the construction of Austin Hall in Leeds, UK. Austin Hall is a purpose built off plan student development comprising of a total of 298 en-suite bedrooms and studios across two separate buildings.
All student bedrooms are arranged in apartments of 4 and 6 bedrooms, each sharing a communal area complete with kitchen, dining area and lounge. Studio rooms are more private and contain their own kitchenette. Situated on Servia Road, the site is a convenient 5 minute walk to The University of Leeds and Leeds Metropolitan University campuses and just a 10 minute walk into the city centre.
Students will benefit from living and studying within a thriving student hub with an abundant of cafes, bars, restaurants and shops. This development is excellently placed to meet this huge demand- this investment opportunity is certainly not to be missed!
Austin Hall | Development Progress 30/06/2017
This update about the development progress of Austin Hall in Leeds is our second update dated from 30/06/2017. Construction works are beginning to edge ever closer to completion, which is expected from next month in July.
The attached report has images and goes into more detail about what works have been completed and how things are progressing. Important points to note are below.
Main Points:
- Floor 6 is near completion. The whole floor is ready for remaining sealants to be applied to any gaps and holes. The builder’s clean can then be undertaken, ready for hand-over.
- Floor 4 and 3 are complete and are waiting for the builder’s clean ready for hand-over.
- The Ground floor, 1st and 2nd floor are still in progress. All the rooms are structurally complete and the rooms are now being painted and carpeted, with furniture installed.
Austin Hall | Development Progress 25/05/2017
This update about the development progress of Austin Hall in Leeds is our very first update dated from 25/05/2017. Austin Hall is progressing well with various aspects of construction now complete. Practical completion date is June 2017.
The attached report has images and goes into more detail about what works have been completed and how things are progressing. Important points to note are below.
Main Points:
- All plastering works are now complete.
- Fire stopping works are now 100% complete.
- All window installations are complete.