Located on an island site between the Leeds Liverpool canal and the famous River Mersey, the Mauretania’s waterside living brings a perspective on life you simply won’t find elsewhere. Built on the historic site of Liverpool’s world heritage docklands, the Aquitania blends its history and present with effortless ease. The ultra-modern apartments are fitted with cutting edge style and sophistication throughout designed to aid a stress-free sanctuary through the use of smart technology.
This unique development offering waterfront living within a vibrant community offers its potential residents a chance to enjoy a luxury lifestyle in an enviable location.

Aquitania | Development Progress 05/02/2024

Dear Investors,

We are pleased to provide the latest update on the construction progress at West Waterloo Place. This update highlights significant milestones achieved and outlines the forthcoming stages of development.

Piling Work: All piling related to the dock wall and combi wall has been completed for the current phase for Aquitania (Block C). Future works in these areas will resume at a later stage of the project.

Concrete Walls: The construction of concrete walls has completed for both Aquitania and Mauretania. We await final connection detail to the Isle of Man (IOM) ferry terminal link and these works will continue at a later stage as part of the projects’ progression.

Block C Developments: The rotary piling for Block C was completed early November. Ground beams, pile caps and concrete completed in December.

Steel Frame Erection for Block C: We have the begun the erection phase of the steel frame. This process is expected to take approximately 6 to 8 weeks and on track to meet our completion target between the end of February to mid March.

Upcoming work: The subsequent phases of the project will include:
• Installation of the metal deck and concreting of the floor levels
• Scaffold construction for the external walls
• Implementation of drainage systems
• Construction of ground floor slabs
• External wall build-up
• Window installation

We aim to achieve water tightness for the entire structure by August, a crucial milestone in the project’s timeline.

Anticipated completion dates for Aquitania and Mauretania:
Aquitania is anticipated to complete by the end of the first quarter (Q1) in 2025. Our team has been diligently working to ensure that all phases of construction align with our schedule, and we are confident in meeting this target.

As of now, the developer is aiming for a Q1 2026 completion date for the Mauretania project. This timeline allows us to maintain a high standard of construction quality and attention to detail throughout the project’s development. They will continue to adhere to stringent safety protocols and comply with all local construction regulations to ensure the safety of our workers and the surrounding community.

Aquitania | Development Progress March 2024

Dear Investor,

We are pleased to provide the latest update on the construction progress at West Waterloo Place. This update highlights significant milestones achieved and outlines the forthcoming stages of development.

Piling: The rotary piling for Block C was completed early November. Ground beams, pile caps and concrete completed in December.
Steel frame: Erected and Completed and fire paint to steel frame in progress.
Metal Deck: Metal deck install in progress and 80% complete with stud welding completed to 50%.
Concrete floors: Works commenced currently 10% complete.
Below ground drainage: Drainage installed and completed.
Below ground masonry: Blockwork completed.
Ground floor slab: Ground floor slab insulated, and mesh re-enforcement completed.
Tanking: Waterproofing to the lift pit completed.
Handrails: Safety Handrails to the perimeter envelope of the building in progress.

March upcoming works will entail:
• First delivery of external brick on-site.
• Steel Formed System delivery and installation.
• Scaffold for the external works to commence.
• Internal walls to commence.
• M&E distribution to commence.

The developer aim to achieve water tightness for the entire structure by August, a crucial milestone in the project’s timeline.
Aquitania is anticipated to complete by the end of Q1 2025.