Ropemaker Place | Development Progress

Here you will find the latest progress reports and images for the construction of the Ropemaker Place in Liverpool, UK. Located at the cross roads of the bustling city centre and the Knowledge Quarter, Ropemaker Place is just moments away from Lime Street Station and Lime Street itself – a street currently being returned to its former eminence with a £35 million regeneration backed by Liverpool City Council.

The local economies and property markets have hugely benefited from multiple large scale regeneration projects, including the £5.6 billion Liverpool Waters. Riding high from positive growth and inward investment, it’s believed that Liverpool is set to take centre stage in 2017.

With the city centre, two universities and Liverpool’s main transport links all on the door step, Ropemaker Place truly has it all making for a highly exciting investment prospect. With rental yields averaging 6% and 7% NET assured for 1 year, this fully managed investment cannot be missed.

Ropemaker Place | Development Progress 09/10/2017

This update about the development progress of Ropemaker Place in Liverpool is dated from 09/10/2017. Below you can see the latest images from the Ropemaker Place site where developers are due next week.

Ropemaker Place | Development Progress 20/10/2017

This update about the development progress of Ropemaker Place in Liverpool is dated from 20/10/2017. Below you can see the latest image from Ropemaker Place where the diggers are onsite and the wall is getting removed.

Ropemaker Place | Development Progress 15/12/2017

This update about the development progress of Ropemaker Place in Liverpool is dated from 15/12/2017. Below you can see the latest images from the Ropemaker Place construction site.

Ropemaker Place | Development Progress 08/02/2017

This update about the development progress of Ropemaker Place in Liverpool is dated from 08/02/2017.

Latest images from the Ropemaker Place construction site and important points from the report are below.

Main Points:

  • Demolition and site clearance as well as ground fill to existing basements are now 100% complete
  • Furthermore, strengthening support to adjacent buildings in addition to the underpinning of adjacent structures is 100% complete.
  • Reinforcement cages to pad and beam footings stand at 95% complete whereas excavation strip footings and concrete strip footings are 90% complete.

Ropemaker Place | Development Progress 07/03/2018

This update about the development progress of Ropemaker Place in Liverpool is dated from 07/03/2018.

Latest images from the Ropemaker Place construction site and important points from the report are below.

Main Points:

  • Underpinning adjacent structures is 100% complete
  • Mass fill concrete foundations pad foundations are 95% complete
  • Excavation strip footings are 90% complete

Ropemaker Place | Development Progress 09/04/2018

This update about the development progress of Ropemaker Place in Liverpool is dated from 09/04/2018. The works are recorded overall to be approximately 3 weeks behind programme, mainly being due to delays with identifying basement structures and enhanced substructure design, gaining access to neighbouring property to undertake strengthening support works requiring alternative design.

Latest images from the Ropemaker Place construction site and important points from the report are below.

Main Points:

  • Consultants design being subject to final construction details
  • Concrete pads and ground beams formed approximately 90% complete
  • Hardcore fill to form levels 90% complete

Ropemaker Place | Development Progress 30/04/2018

This update about the development progress of Ropemaker Place in Liverpool is dated from 30/04/2018. Subsequent to a slight delay due to difficulties in identifying some basement structures as well as an alteration to the substructure design, everything is going to plan at Ropemaker Place with the steel frame structure now clearly visible from the roadside.

Latest images from the Ropemaker Place construction site and important points from the report are below.

Main Points:

  • Ground fill to basements is 100% complete
  • Concrete pads, ground beams and hardcore fill are 90% complete.
  • The steel frame structure is 85% complete

Ropemaker Place | Development Progress 31/05/2018

This update about the development progress of Ropemaker Place in Liverpool is dated from 31/05/2018. Demolition of adjoining structures, perimeter walls and site clearance Demolition of adjoining structures, perimeter walls and site clearance.

Latest images from the Ropemaker Place construction site and important points from the report are below.

Main Points:

  • finishesFlat roof structures and finishes
  • External balconies and balustrades
  • Installation of electrical services Installation of electrical services

Development Enquiry Form