Here you will find the latest progress reports and images for the construction of The Chavasse Building in Liverpool, UK. The Chavasse Building is situated in one of the city’s hottest up-and-coming districts, Ropewalks. Also known as Liverpool’s ‘independent quarter’, this central area of Liverpool has seen astonishing redevelopment, attracting £100 million worth of investment in recent years.

The Chavasse Building offers luxurious micro, 1 and 2 bedroom apartments at the heart of Liverpool’s city centre, nightlife and culture as well as its proximity to the Universities. A boutique development of 47 apartments, every unit in the building benefits from spacious floorplans and high spec finish. It also provides excellent communal areas such as a fully equipped gym and a Japanese inspired ‘Zen’ rooftop garden for all residents to enjoy.

With a 7% NET rental assurance in place for the 1st year and managed by the award winning Urban Bubble, this hands-off investment will allow you to benefit from not only a great rental income, but also fantastic capital value uplift.

The Chavasse Building | Development Progress 04/02/2019

This update about the development progress of The Chavasse Building in Liverpool is dated from 04/02/2019.

Weeks 54-62

  • Mac Roofing coping to top deck.
  • Mac Roofing 5th floor quadcore cladding 40% complete.
  • Window pressings.
  • M&E 1st fix 85% complete.
  • M&E 1st fix works in progress to communal areas.
  • Joinery 1st fix works in progress.
  • Super structure brick work complete.
  • External mastic to moving joints 45% complete
  • Sub mains and distribution 80% complete.
  • 1st floor apartments tape and joint in progress.
  • 2nd floor closing up of apartments & tape and joint in progress.
  • Brick clean ongoing to all elevations.
  • Mist coat paint

Download Update

The Chavasse Building | Development Progress 04/12/2018

This update about the development progress of The Chavasse Building in Liverpool is dated from 04/12/2018.

Weeks 38-43

  • Mac Roofing commenced ‘hot melt’ works to 5th floor terrace.
  • Mac Roofing Topdeck works 95% complete.
  • Window and door install 95% complete.
  • M&E riser cupboards under construction.
  • M&E 1st fix works in progress to communal areas and Apts.
  • Joinery 1st fix works now in progress.
  • Super structure brick work continuing in progress externally at 4th & 5th floors to all elevations.
  • Lift shaft block work in 100% complete.
  • Ancon masonry support 1st, 3rd & 5th floors installed.
  • Scaffold works in complete to existing sub-station external elevations.
  • Internal Apt partitions now in progress.

Download Update

The Chavasse Building | Development Progress 31/10/2018

This update about the development progress of The Chavasse Building in Liverpool is dated from 31/10/2018.

Main Progress from weeks 30 – 38:

  • Intumescent paint sprayed to all internal structural steel now complete to available areas.
  • Windposts to 5th floor procured and installed.
  • SFS install now 100% with Siniat board installation now also complete to available areas.
  • Window and door install 80% complete.
  • Super structure brick work continuing in progress externally at 3rd floor to all elevations other than over existing sub-station.
  • Sub-station build complete.
  • Lift shaft block work in 95% complete.
  • Undercroft car park.
  • Mac Roofing commenced Topdeck works.
  • Ancon masonry support 1st, 3rd & 5th floors on site.
  • Scaffold works in progress to existing sub-station external elevations.
  • Internal Apt partitions now in progress.
  • M&E 1st fix works in progress to communal areas and Apts.

Download Update

The Chavasse Building | Development Progress 03/09/2018

This update about the development progress of The Chavasse Building in Liverpool is dated from 03/09/2018.

Main Progress from weeks 19 – 25:

  • Roofing materials have been issued to planning for approval
  • Levels in undercroft car park have been built up to omit the need for a retaining wall along grid line 9 – 16
  • Agreement in principal to build scaffold along Grid line 5 from inside SP Energy boundary
  • Preliminary report received from Omega Fire Engineers detailing proposed fire strategy. Now distributed to sub-contractors. Design development now in progress with specialist contractors.
  • Report received from Environoise Acoustic Consultants detailing acoustic requirements for the building envelope and internal partitions.
  • Base Energy design ongoing with communication via architects.
  • On-going design with regards to incoming services. Works in progress.
  • On-going procurement of remaining sub-contract packages in line with build programme.
  • A strategy is ongoing to condense the current programme in order to recover any lost time due to inclement weather.

Download Update

The Chavasse Building | Development Progress 07/08/2018

This update about the development progress of The Chavasse Building in Liverpool is dated from 07/08/2018.

Main Progress from weeks 19 – 25:

  • All service ductwork laid within building footprint.
  • Intumescent paint sprayed to all internal structural steel.
  • Ductwork and HV cables laid across carriageway for connection to SP network at later date.
  • Slab poured for substation.
  • Retaining wall built along GL A 5-9.
  • LV cables puled from commercial units back to substation ready for connection at later date.
  • Installation of SFS floors 1-3.
  • Sub structure drainage now 100% complete with multiple visits from building control.
  • All sub structure brickwork completes up to DPC.
  • First section of scaffold erected for installation of goods hoist.
  • First phase of substation brickwork completed.
  • U.U. engineer attended site to survey both commercial units and also apartments water connection.
  • All slab insulation and reinforcement mesh installed as per structural engineer’s drawings.
  • Ground floor slab concrete placed.

The Chavasse Building | Development Progress 15/06/2018

This update about the development progress of The Chavasse Building in Liverpool is dated from 15/06/2018.

Main Progress from weeks 12 – 19:

  • Installation of concrete stairs
  • Completion of phased install of steel frame
  • Steel frame line level by Leach engineer and handed over to CCL
  • Provision for lightning protection fitted to steel frame
  • Landscaping to Pagoda car park
  • Easy edge inspected and signed off
  • Metal deck sheeting and Ancon support edge trim installed on all floors
  • Sub structure lift pit foundations installed
  • Building perimeter ground cleared in preparation for sub structure brick work
  • Shear stud and Re-enforcement bar installed to all floors
  • First floor concrete slab poured
  • Groundworkers in progress with sub-structure service ductwork
  • Materials and plant on site for Cara brickwork SOS Monday 18th
  • Cara brickwork in progress with perimeter sub structure brickwork
  • Concrete slab placed on floors 2 & 4

The Chavasse Building | Development Progress 19/06/2018

This update about the development progress of The Chavasse Building in Liverpool is dated from 19/06/2018. The frame of the building is now up, see below for images.

The Chavasse Building | Development Progress 04/05/2018

This update about the development progress of The Chavasse Building in Liverpool is dated from 04/05/2018. Bora complete all 1st phase of ground works concrete pads and strip foundations ahead of Structural Steel start on site(SOS).

The attached report goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • Bora prepped ground for structural steel erection.
  • Quality assurance in line with site progress including phased handover of steel frame.
  • Remaining strip foundations where set out, inspected by Building Control and concrete placed.

The Chavasse Building | Development Progress 12/03/2018

This update about the development progress of The Chavasse Building in Liverpool is our very first update dated from 12/03/2018. Good progress has been made over the past 3 weeks even with the adverse weather conditions we have had over the past two weeks.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • Groundworkers provided additional labour and also an 8 ton excavator and 6 ton dumper to carry out all works required. We started by completing a reduce level dig from grid line 5 – 16 removing around 600 ton of spoil off site.
  • Weather conditions prevented the concrete pour taking place until Monday 5 th March. Bolt jigs again set by Groundworks Engineer
  • Scottish power engineer came to site 7th March to investigate termination of power, he has now booked work in and can take up to 10 days for work to be complete.

The Chavasse Building | Development Progress 02/02/2018

This update about the development progress of The Chavasse Building in Liverpool is our very first update dated from 02/02/2018. During January (weeks 10-13) we have suffered a period of inclement weather that has had a slight impact on the progress we would have liked to have made.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • Due to the slight delay on progress, the groundworkers are mobilising additional labour for week commencing Monday 12th February, along with the additional labour there will also be additional plant/machinery
  • Crossfield will be bringing in a new Site Manager (John Farrell ) to work under Contracts Manager, Scott Sherwood, as the site will require additional management due to increased resources and heavy plant
  • External drainage dig/survey has been carried out and inlet levels have been inspected and design submitted

The Chavasse Building | Development Progress 11/01/2018

This update about the development progress of The Chavasse Building in Liverpool is our very first update dated from 11/01/2018. A meeting has been held on site with LCC and Amey to assess and audit our road closure and site hoarding, a local councilor was also invited to engage with the local community.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • LCC agreed that we can suspend the “No Entry” to Suffolk Street enabling a 2 way system.
  • Bora conducted the GW site survey to position foundations and also transfer Datum level on to site.
  • The area of GL 1-4 was assessed surveyed by waste management company and demarcated appropriately.

The Chavasse Building | Development Progress 30/11/2017

This update about the development progress of The Chavasse Building in Liverpool is our very first update dated from 30/11/2017. The works on site commenced at the beginning of November starting with the “soft strip” of any unwanted waste that had accumulated on site, and a thorough examination of the area for sharps/needles etc.

The attached report goes into more detail about what works have been completed and how things are progressing. Important points to note are below.

Main Points: 

  • Sumo Survey carried out.
  • Site clearance of weeds and waste materials.
  • Traffic management erected.